Closeout

Closeout of Discretionary/Categorical and Block/Formula Awards

Jump to Section:
Cash Reconciliation and Final Draw Down
Recipient Closeout Requirements

Cash Reconciliation and Final Draw Down

As the award recipient, you provide a financial reconciliation of your accounting records to the Federal Financial Report (FFR) at closeout.

  • Any match must be reported on the final FFR (SF-425).
  • Obligations incurred prior to the project period end date must be liquidated no more than 90 days after the project period end date.
  • Recipients must request final reimbursement (draw down) of Federal expenditures made within the approved project period in conjunction with the final SF-425.

[ back to top ]

Recipient Closeout Requirements

Within 90 days of the end date of the award (or any approved extension), the following must be submitted by the recipient to the awarding agency:

  • Final SF-425
  • This FINAL report of expenditures must have no unliquidated obligations.
  • Any unobligated or unexpended funds will be de-obligated from the award amount. Make sure you have obligated or expended as much as possible of your funds prior to the award end date.
  • Match requirements must be met by the end of the award period and included in the report.
  • Recipients who have drawn down funds in excess of their Federal expenditures must return unused funds to the awarding agency when they submit the final report.
  • Be sure to reconcile your final FFR to your internal accounting records. All entries to the accounting system must be supported by adequate source documentation (for example, original invoices and contracts).
  • Report all allowable costs incurred, both at the recipient and subrecipient level.
  • The final progress report should be prepared in accordance with instructions provided by the awarding agency???s program office.
  • All inventions that were conceived or first actually reduced to practice during the course of work under the award project must be listed on an invention report before closeout.

box with checkmarkAction Item

Submit your final SF-425, final progress report, and an invention report (if applicable) well in advance of the end of the 90-day period. Once an administrative closeout begins, you will be unable to draw any additional funds on the award.